BREEAM NOx emissions
Contents |
[edit] Aim and benefits
Under BREEAM UK New Construction, the aim of this credit is to minimise NATIONAL NOx emissions.
There is slight variance to this aim in BREEAM International, where fully electrically heated premises are awarded the credits by default as there are no on site emissions.
[edit] When to consider
[edit] Stage 2
Mechanical Engineer calculates that their concept achieves credits. They tell BREEAM assessor to target 3 credits. This should then gets written into the ERs, ideally in an M&E document and in a BREEAM document.
[edit] Stage 3
Mechanical Engineer doing Stage 3 design should calculate their design still achieves 3 credits. This may be the contractor's engineer, or could still be the client side engineer, depending on how the project is being tendered.
[edit] Stage 4
If there was a design change, as part of either:
The technical submission to the client team regarding the design change, the POL 02 credits should have been recalculated by the contractor side mechanical engineer and approved by the client side engineer,
OR
The client side mechanical engineer should recalculate the POL 02 credits, and confirm their new design complies.
[edit] Stage 5
The contractor's Mechanical Sub Contractor should submit a technical submittal for the kit they propose is procured including updated POL 02 calculations. The AP and/or M&E designers should approve the technical submittal having checked the proposed kit meets POL 02 (among other) requirements.
The contractor should submit purchase orders/delivery notes to BREEAM assessor, along with as built heating/hot water drawings/schematics.
The BREEAM assessor should then confirm accuracy during their site inspection.
[edit] Step by step guidance
Awaiting content
[edit] Questions to ask while seeking compliance
Do you have any electric heating?
Be wary under BREEAM UK New Construction as the NOx emissions for electric heating are so high, that a couple of electric heaters (over the door? small quantity of office areas in an otherwise unheated building?) can make it nearly impossible to achieve many credits.
Did you include the domestic hot water (DHW) heating system into the calculation?
DHW heating can be excluded from the calculation where designer can demonstrate it is less than 10% of the building's total energy consumption (e.g. via Building's Energy Performance Certificate). Point of use water heaters are excluded by default.
Does the calculation use values for sources' operation under normal conditions to meet the building’s heating demand?
Normal conditions means without any redundant capacity, stand-by or back-up source for maintenance or emergency heating.
Does the project incorporate a new CHP? or is it being connected to an existing CHP system?
The reason to ask this is because the NOx for the CHP system will have to be calculated separately, and under BREEAM 2014 UK New Construction schemes and earlier, the methodology is very favourable to CHP leading to more available credits. Note: under BREEAM 2018 UK New Construction this is not the case.
BREEAM UK New Construction 2014 Issue 5.0 Criteria - POL 02
BREEAM International New Construction 2016 Issue 2.0 Criteria - POL 02
[edit] Tools and resources
Awaiting content
[edit] Tips and best practice
District heating system:
For project connected to the district heating system which is not under the developer's control and mandated by a local authority (or other statutory body) maximum number of credits to be awarded. Where this is not mandatory the NOx emissions calculation to be provided. (see KBCN0979) Where a district heating system also generates electricity, this can be used to off-set NOx emissions from grid electricity, the calculation methodology for CHP systems can be used. (see KBCN0857)
[edit] Typical evidence
Typical design stage evidence may include:
- Boiler/CHP/Heat Emitter/Cooling/Heater schedules
- Drawings showing quantity of each item of heating/hot water/cooling equipment
- Datasheets and/or manufacturer emails confirming NOx emissions for each piece of equipment
- Letter or calculation sheet (be careful that a calc sheet is robust - signed? dated?) calculating the NOx emissions for the development.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
[edit] Find out more
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Sandra Turcaniova 15:11, 03 Jan 2018 (BST)
[edit] Related articles on Designing Buildings
- Air Quality Taskforce.
- Air quality.
- At a glance - Indoor air quality.
- BREEAM and air quality.
- BREEAM Indoor air quality plan.
- BREEAM Indoor air quality Ventilation.
- BREEAM Indoor pollutants VOCs.
- BREEAM.
- Bringing a breath of fresh air to the design of indoor environments.
- BSRIA responds to UK Air Pollution Report.
- Ensuring good indoor air quality in buildings.
- Fresh air.
- High pollution location.
- Indoor air quality.
- Indoor environmental quality.
- Locating ventilation inlets to reduce ingress of external pollutants into buildings: A new methodology IP 9 14.
- Pollution.
- Sources of external pollution.
- Submittals.
- Ultra Low Emission Zone.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).