BREEAM NOx emissions
Contents |
[edit] Aim and benefits
Under BREEAM UK New Construction, the aim of this credit is to minimise NATIONAL NOx emissions.
There is slight variance to this aim in BREEAM International, where fully electrically heated premises are awarded the credits by default as there are no on site emissions.
[edit] When to consider
[edit] Stage 2
Mechanical Engineer calculates that their concept achieves credits. They tell BREEAM assessor to target 3 credits. This should then gets written into the ERs, ideally in an M&E document and in a BREEAM document.
[edit] Stage 3
Mechanical Engineer doing Stage 3 design should calculate their design still achieves 3 credits. This may be the contractor's engineer, or could still be the client side engineer, depending on how the project is being tendered.
[edit] Stage 4
If there was a design change, as part of either:
The technical submission to the client team regarding the design change, the POL 02 credits should have been recalculated by the contractor side mechanical engineer and approved by the client side engineer,
OR
The client side mechanical engineer should recalculate the POL 02 credits, and confirm their new design complies.
[edit] Stage 5
The contractor's Mechanical Sub Contractor should submit a technical submittal for the kit they propose is procured including updated POL 02 calculations. The AP and/or M&E designers should approve the technical submittal having checked the proposed kit meets POL 02 (among other) requirements.
The contractor should submit purchase orders/delivery notes to BREEAM assessor, along with as built heating/hot water drawings/schematics.
The BREEAM assessor should then confirm accuracy during their site inspection.
[edit] Step by step guidance
Awaiting content
[edit] Questions to ask while seeking compliance
Do you have any electric heating?
Be wary under BREEAM UK New Construction as the NOx emissions for electric heating are so high, that a couple of electric heaters (over the door? small quantity of office areas in an otherwise unheated building?) can make it nearly impossible to achieve many credits.
Did you include the domestic hot water (DHW) heating system into the calculation?
DHW heating can be excluded from the calculation where designer can demonstrate it is less than 10% of the building's total energy consumption (e.g. via Building's Energy Performance Certificate). Point of use water heaters are excluded by default.
Does the calculation use values for sources' operation under normal conditions to meet the building’s heating demand?
Normal conditions means without any redundant capacity, stand-by or back-up source for maintenance or emergency heating.
Does the project incorporate a new CHP? or is it being connected to an existing CHP system?
The reason to ask this is because the NOx for the CHP system will have to be calculated separately, and under BREEAM 2014 UK New Construction schemes and earlier, the methodology is very favourable to CHP leading to more available credits. Note: under BREEAM 2018 UK New Construction this is not the case.
BREEAM UK New Construction 2014 Issue 5.0 Criteria - POL 02
BREEAM International New Construction 2016 Issue 2.0 Criteria - POL 02
[edit] Tools and resources
Awaiting content
[edit] Tips and best practice
District heating system:
For project connected to the district heating system which is not under the developer's control and mandated by a local authority (or other statutory body) maximum number of credits to be awarded. Where this is not mandatory the NOx emissions calculation to be provided. (see KBCN0979) Where a district heating system also generates electricity, this can be used to off-set NOx emissions from grid electricity, the calculation methodology for CHP systems can be used. (see KBCN0857)
[edit] Typical evidence
Typical design stage evidence may include:
- Boiler/CHP/Heat Emitter/Cooling/Heater schedules
- Drawings showing quantity of each item of heating/hot water/cooling equipment
- Datasheets and/or manufacturer emails confirming NOx emissions for each piece of equipment
- Letter or calculation sheet (be careful that a calc sheet is robust - signed? dated?) calculating the NOx emissions for the development.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
[edit] Find out more
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Sandra Turcaniova 15:11, 03 Jan 2018 (BST)
[edit] Related articles on Designing Buildings
- Air Quality Taskforce.
- Air quality.
- At a glance - Indoor air quality.
- BREEAM and air quality.
- BREEAM Indoor air quality plan.
- BREEAM Indoor air quality Ventilation.
- BREEAM Indoor pollutants VOCs.
- BREEAM.
- Bringing a breath of fresh air to the design of indoor environments.
- BSRIA responds to UK Air Pollution Report.
- Ensuring good indoor air quality in buildings.
- Fresh air.
- High pollution location.
- Indoor air quality.
- Indoor environmental quality.
- Locating ventilation inlets to reduce ingress of external pollutants into buildings: A new methodology IP 9 14.
- Pollution.
- Sources of external pollution.
- Submittals.
- Ultra Low Emission Zone.
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.